Skip to the content
The Maryland-National Capital Park and Planning Commission
Home / News / Planning Board Approves New Plans for Clarksburg Town Center at July 23 Meeting

Planning Board Approves New Plans for Clarksburg Town Center at July 23 Meeting

Revised design of commercial core, new community facilities and upgrades to local parks part of proposal to complete east and west sides of Town Center

SILVER SPRING, MD  The Montgomery County Planning Board, part of the Maryland-National Capital Park and Planning Commission (M-NCPPC), has approved new plans for the Clarksburg Town Center submitted by Third Try, LLC of McLean, VA. These project, preliminary and site plan amendments are limited to the unbuilt portions of the 270-acre Town Center, on both the east and west sides of the development. They include a revised design of the commercial core, new community and civic buildings, and upgrades to two local parks.

When implemented, the plans will complete the Clarksburg Town Center after years of delay, due to numerous violations associated with the build-out of the community. An agreement reached by a citizen-led group known as the Clarksburg Town Center Advisory Committee and developer NNPII Clarksburg LLC (Newlands) led to a new site plan in 2009, calling for significant improvements to the Town Center.  However, Newlands did not move forward with these plans, eventually selling the unfinished portions of the property to Third Try.

The Town Center currently includes approximately 840 occupied residential units, a new elementary school, landscaping along major roads and other improvements. The plans reviewed at the July 23 Planning Board meeting call for a total of 1,120 residential units, along with 206,185 square feet of commercial space and numerous community enhancements.

Mixed-use, neo-traditional core

The commercial core on the west side of the Greenway will include office and medical buildings, retail, restaurants and a grocery store. The buildings are oriented toward General Store Drive (a private street segment) and Clarksburg Square Road with surface parking located in the rear so the core is compatible with existing development.

Amenities in the commercial core include a plaza with a splash fountain and seating. A civic building and a town green are proposed to the north, across Clarksburg Square Road. The town green is envisioned to include a stage with amphitheater seating for community-wide events. The neo-traditional design of the mixed-use Town Center is meant to complement existing structures and the Clarksburg Historic District at its heart.

Community buildings and open spaces

The Planning Board also approved plans for a new, 3,200-square-foot community building adjacent to the Residents’ Club to host large, indoor gatherings. A much-needed parking area located in nearby Sinequa Square will serve the club pool and both community buildings.

Also approved are improvements to Piedmont Woods and Kings Pond Local Parks. A basketball court, tennis courts, a playground, a dog park, picnic shelters and hiking trails are proposed for Piedmont Woods Local Park. A pond with a fishing pier, a tot lot, a hiking trail and picnic shelters will be added to Kings Pond Local Park.

A land bridge across the Greenway will connect the east and west sides of the Town Center. The Greenway will be enhanced to support stormwater management and reforestation. The Planning Board recommended that a natural surface walking trail be provided within the Greenway. A shared-use path will also connect Clarksburg and Stringtown Roads.

At the Planning Board meeting, Deputy Director of the Planning Department, Rose Krasnow, who has been involved with this development since the first violations were alleged, expressed the sentiments of many when she said, “It has taken a long time to get to this point, but with the approval of these plans today, we believe that the ultimate vision of Clarksburg Town Center as a walkable, mixed-use hub with a small-town feel and numerous amenities for residents can finally be realized.”

Background on Clarksburg Town Center

In 1994, the Montgomery County Council approved the Clarksburg Master Plan and Hyattstown Special Study Area, calling for the creation of a Town Center. This Center focused on the Clarksburg Historic District and would include a mix of uses. Two years later, plans were approved for a neo-traditional community to be constructed in phases with residential units, offices and retail. By 2006, about 725 units of the approved 1,300 dwelling units had been built or were under construction. The retail phase was never approved.

In 2005, the Clarksburg Town Center Advisory Committee alleged numerous violations associated with the build-out of the community and the Planning Board held several hearings on the allegations. Mediation between the advisory committee and developer led to an amended site plan, which became known as the Compliance Plan and was approved by the Planning Board in 2006.

In 2009, the Planning Board approved planning applications for commercial spaces, more than 1,200 dwelling units, a waiver to reduce the number of parking spaces and reconfirmation of building setbacks from residentially zoned properties. Although many of these elements were recommended in the Compliance Plan, the Board did not require that all elements of that Plan be realized, such as parking structures in the retail core. Subsequent plan amendments approved by the Board in 2010 and 2013 have resulted in the completion of some additional dwellings and community improvements.