Monitoring Report
Although not required by the Shady Grove Sector Plan, the Biennial Master Plan Monitoring Report (July 2015) provides the status of new development, public facilities, and staging. There are significant public investments associated with the County Executive’s “Smart Growth Initiative ” and moving the recommended development into the next stage. The Shady Grove section of the monitoring report is from pages 61 to 71.
Staging
All of the Stage 1 triggers have been implemented. The table below provides an update of the approved development and its relationship to Stage 1:
Sector Plan | Residential Development | Non-Residential Jobs |
---|---|---|
Stage 1 limits with County Service Park Redevelopment | 2,540 dwelling units | 1,570 jobs |
Allocated Development
| ||
120120080: Shady Grove Station Preliminary Plan | 2,210 dwelling units | 630 jobs
41,828 sf (retail; 400 sf per job): 104 jobs 131,422 sf (office; 250 sf per job): 526 jobs |
120090100: P146 Shady Grove Metro (Somerville property) Preliminary Plan | 156 dwelling units | N/A |
Total Approved Development (Summer 2014)
|
2,366 dwelling units
|
630 jobs
|
Remaining Stage 1 Development
|
174 dwelling units
|
940 jobs
|
The following items are Stage 2 triggers:
- Evaluate the need and schedule of the new elementary school and ask MCPS to begin planning and program accordingly.
- Fund acquisition or dedication for a local park with at least one adult-sized ball field. If County Service Park relocates, dedication of required park facilities should be required as part of the preliminary plan approval of private development. Fund construction for one park.
- The Planning Board will consider the aggregate performance of all TMAgs in the Shady Grove Policy Area in the decision to move to Stage 2. If sum total of vehicle trips from all participating sites exceeds the sum of the allowed trip caps, then the plan should not be considered ready to move to the subsequent stage.
- Each of the major intersections in the Sector Plan area must operate at or better than its respective Growth Policy Local Area Transportation Review (LATR) level of service standard or congestion level at the time of the Plan’s adoption, whichever is greater. Traffic will be measured from existing and approved development on a network programmed for completion four years later.
- Fund the Metro Access Partial Interchange for completion within the first four years of the Capital Improvements Program to ensure adequate access to the Metro station.
- Fund the MD 355/Gude Drive interchange for completion within the first four years of the Consolidated Transportation Program, the Capital Improvements Program, or other transit or transportation improvements that would make the intersection function at an acceptable level. ‘Acceptable’ is defined as the applicable intersection congestion standard in the Growth Policy.
- Planning Board must make determination that Stage 2 can proceed.